Personnel
One certified electrician
Safety
WARNING
Before installing the charging station, refer to safety instructions.
WARNING
Risk of Electrocution
There is a risk of electric shock. Do not alter, relocate, drill, or remove any component without consulting with an EV Meter certified team.
WARNING
Local Electrical Regulations
All installation actions must be done by a certified electrician and according to the local regulations.
What is in the Box
- Installation Manual
- Warranty
- 6 × M4 Allen Screws
- Bottom Tightening Screw Kit
- Bracket
- Charging Station
Tools and Equipment
- Phillips bit
- Level
- Drill
- Allen bit
- Hammer
Materials
- M10 Stainless Steel bolts and nuts
- M4×10 Allen Screws
- M3×12 stainless steel Phillips screws
- flexible N2XY 5X6 mm² Cable
- Dowels
- Power Cable
- Charging Station Kit
Preparations
NOTICE
Pay attention! There is a QR code in the last page of the installation guide.
Save the QR code for Charging Station synchronization in the App.
NOTICE
Kit Unboxing
The kit unboxing is to be performed only by a certified electrician followed by a visual check for any damaged/ broken parts. In case of any damage, contact EV Meter support.
- Unbox the charging station kit.
- Make sure a circuit breaker is installed in the electrical panel, according to the following table:
Connection type | Max Power output | Circuit breaker |
---|---|---|
1 Phase | 7.4 kW | 1×32 A |
3 Phase | 22.1 kW | 3×32 A |
- Insert the cables from the circuit braker into a flexible N2XY 5X6 mm² cable. Make sure the cable’s diameter is 18 mm and the cables are long enough to reach the charging station.
- Turn off the charger power using the circuit breaker.
- Using a voltmeter or any equivalent device, make sure that all the power to the charger is turned off.
NOTICE
To provide quick power off, in case of emergency or maintenance, install an emergency switch, according to the local regulations and the power input to the charging station.
EV Meter recommend installing an emergency switch specifically for the charging station, next to the charging station.
Installation Overview
CAUTION
Installation Conditions
The installation must be performed in dry conditions.
The installation process includes the following steps:
- Charger Wall Mounting Bracket Installation
- Charger Mounting
- Electrical panel Power Cable Connection
- Charger Assembly
- Charger Synchronization
Charger Wall Mounting Bracket Installation
- Place the charger wall mounting bracket on the wall.
- Using a drill, drill three holes, according to the holes placement in the charger wall mounting bracket.
- Using a hammer, hammer three dowels into the holes.
- Using a screwdriver, three M10 screws, and nuts, secure the wall mounting bracket.
- The wall mounting bracket is attached to the wall.
Charger Mounting
- Open the Charging Station Cover.
NOTICE
Pay attention to the cables connections to the Charger Cover.
Take note of which cable is connected to which connector, to use in the Charger Assembly process.
- Disconnect the cables from the Charging Station Cover.
- Put the charger cover back in the box.
- Align the sockets on the charger with the anchors on the charger wall mounting bracket.
- Place the charger on the wall mounting bracket.
- Using Phillips screw and Phillips screwdriver, install the screw on the bottom of the charger, to secure the charger to the charger wall mounting bracket.
Electrical Panel Power Cable Connection
WARNING
Risk of Fire
There is a risk of fire. Do not alter, relocate, drill, or remove any component without consulting with an EV Meter certified team.
CAUTION
Cable Placement
Make sure the cable is not placed in the way of any pedestrians, vehicles, or objects.
- Using a Phillips bit, remove the two screws securing the cable shield at the bottom of the charger.
- Remove the cable shield.
- Remove the cable gasket.
- Insert the 5X6 mm² cable trough the gasket.
- Insert the 5X6 mm² cable trough the designated socket.
- Make sure the gasket is properly fitted in the socket.
- Using a Phillips bit, unscrew the cable catch screw.
- Using the cable catch, secure the cable.
- Using a Phillips bit, secure the cable catch screw.
- Using an Allen bit, unscrew four M3×10 Allen screws securing the phase connectors’ shield.
- Remover the phase connectors’ shield.
- Connect the 5X6 mm² cable to the charger according to the following diagram and the stickers.
- Install the phase connectors’ shield.
- Using an Allen bit, screw the four M3×10 Allen screws to secure the phase connectors’ shield.
- Install the cable shield.
- Using a Phillips bit, screw two M3×12 Phillips screws to secure the cable shield.
Charger Assembly
- Connect the charger cables previously disconnected, to the charger cover according to the note taken in charger mounting process.
CAUTION
Falling Parts
Keep holding in place the Panel Cover until it is fully attached to the Front Panel, to prevent it from falling.
- Place the charging station cover on the charger.
- Using an Allen bit while holding the charger cover in place with one hand, screw six M4×10 Allen screws to secure the charger cover to the charger.